Report a problem

Every Maven project builds with the same commands. mvn package makes a JAR of a library and a WAR of a web application; mvn verify builds and checks either one. The person who runs the build says how far the build should go. The project decides what happens on the way there. Three ideas make that split work: the lifecycle, its phases, and the plugin goals bound to those phases.

A lifecycle is a fixed list of phases

Maven has three lifecycles. The default lifecycle builds, tests and ships the project. The clean lifecycle removes what an earlier build produced. The site lifecycle generates the project's website.

Each lifecycle is a list of phases in a fixed order. The phases of the default lifecycle that you call from the command line are:

Phase What happens
validate Check that the project is complete and correct.
compile Compile the source code.
test Run the unit tests against the compiled code.
package Package the compiled code, for example into a JAR file.
verify Run integration tests and other checks on the package.
install Copy the package into the local repository, for other projects on your machine.
deploy Copy the package to a remote repository, for other people.

Between these are phases such as generate-sources, process-resources, test-compile and prepare-package. The lifecycles reference lists every phase of the three lifecycles.

When you name a phase, Maven runs all phases before it in the same lifecycle first. That is why mvn package runs the tests: test comes before package, and a JAR is only made from code that passed its tests. It is also why one command is enough. mvn install compiles, tests, packages and verifies before it installs, so there is no need to call each step.

You can name phases of different lifecycles in one command. mvn clean package runs the clean lifecycle up to clean, and then the default lifecycle up to package.

Plugin goals do the work

A phase is a name for a step. It does nothing by itself. The work is done by plugins: each plugin is a Java library with one or more goals, and each goal is one task. The Compiler plugin has a compile goal for your code and a testCompile goal for your tests. When a goal is bound to a phase, it runs every time the build passes that phase. A phase with no goal bound to it is skipped without notice.

The build output names each goal it runs:

[INFO] --- compiler:3.13.0:compile (default-compile) @ my-app ---

This line reads as: the compile goal of the plugin with prefix compiler, version 3.13.0, in the execution default-compile, for the project my-app.

You can also run a goal on its own, with prefix:goal on the command line. mvn dependency:tree runs only the tree goal of the Dependency plugin, and no phases. Goals and phases mix: mvn clean dependency:copy-dependencies package cleans, then copies the dependencies, then runs the default lifecycle up to package, in that order.

Options that seem to change the lifecycle usually belong to a goal. -DskipTests does not leave out the test phase; it tells the Surefire plugin's test goal to run no tests, and the goal logs Tests are skipped.

The packaging decides the default goals

Which goals a phase runs depends first of all on the project's packaging, the <packaging> element of the POM. A project without one has packaging jar, and gets these goals:

Phase Goal
process-resources resources:resources
compile compiler:compile
process-test-resources resources:testResources
test-compile compiler:testCompile
test surefire:test
package jar:jar
install install:install
deploy deploy:deploy

Packaging war binds the same goals, with war:war instead of jar:jar. Packaging pom, used for parent projects that only hold configuration, binds nothing but install:install and deploy:deploy, because there is nothing to compile. The plugin bindings reference lists the bindings for every packaging.

So mvn package means “compile, test and make a JAR” in one project and “compile, test and make a WAR” in another, and you do not need to know which before you run it.

Plugins in the POM add goals

To add a step to the build, you add a plugin to the <build> section of the POM, with an execution that names the goal. This makes the build also package the source code:

pom.xml

<build>
  <plugins>
    <plugin>
      <artifactId>maven-source-plugin</artifactId>
      <version>3.4.0</version>
      <executions>
        <execution>
          <goals>
            <goal>jar-no-fork</goal>
          </goals>
        </execution>
      </executions>
    </plugin>
  </plugins>
</build>

A goal declares the phase it belongs to by default. jar-no-fork belongs to package, so mvn package now writes my-app-1.0-SNAPSHOT-sources.jar next to the JAR. When several goals are bound to the same phase, the goals of the packaging run first, then the goals from the POM in the order they appear there; here, jar:jar runs before source:jar-no-fork.

To bind a goal to another phase, name the phase in the execution with <phase>verify</phase>. A plugin can have several executions, each with its own goals, phase and configuration; Configuring plugins describes them.

Plugin versions belong in the POM

The goals in the default bindings come from plugins whose version you did not choose. When the POM does not set one, Maven uses a default that belongs to the Maven release: Maven 3.9.16 builds a JAR with maven-jar-plugin 3.5.0, Maven 3.10.0 with 3.5.1. The same project can then build differently on two machines.

That is why the project from the quickstart archetype lists every plugin of the default bindings, with a version, in <build><pluginManagement>. Setting the versions there fixes them for every build of the project, whichever Maven runs it.

Maven 4: Maven 4 warns when a plugin of the default bindings has no version in the POM: Version not locked for default bindings plugins [maven-resources-plugin, maven-compiler-plugin, ...], you should define versions in pluginManagement section of your pom.xml or parent.

Call verify, not integration-test

The phases whose names start with pre-, post- or process- prepare or finish the work of the phase next to them. They produce intermediate results, and you do not normally call them.

Integration tests show why. A plugin that starts a server for the tests binds a goal to pre-integration-test, the tests run in integration-test, and the server is stopped in post-integration-test. Reports are checked in verify. In Maven 3, mvn integration-test stops after the integration-test phase: the server keeps running and no report is checked. mvn verify runs the whole sequence, which is why it is the command to call when you want to know whether the project builds and works.

Maven 4: The default lifecycle is a tree of phases, each with a before: and an after: step, such as before:compile and after:compile. The Maven 3 names remain as aliases: prepare-package is before:package, process-classes is after:compile, pre-integration-test and post-integration-test are before:integration-test and after:integration-test. When you call a phase, Maven 4 runs its after: step as well. mvn integration-test therefore also runs post-integration-test, mvn compile also runs process-classes, and mvn prepare-package runs up to and including package. Maven 4 also adds phases such as sources, resources and ready (compiled and ready to use). The Maven 4 lifecycles reference lists them.